The 2024 guidelines require a comprehensive Safety case: safety of personnel, equipment, and the environment is paramount. Judges grade each team’s plan and implementation.
Key expectations:
- Safety plan: identify foreseeable hazards and mitigations beyond PPE, including handling rock, rotating machinery, electrical shock, and communication during operations. Keep the plan current throughout the project.
- Guards and interlocks: rigs often spin components at high RPM; include protective covers/shields so loose parts cannot become projectiles. Provide emergency stops and appropriate interlocks.
- Lab practices: supervision, lockout/tagout where applicable, and safe test procedures.
Mandatory Rule
- Teams MUST maintain an up‑to‑date written Safety plan.
- Rigs MUST include guards/shields, appropriate interlocks, and clearly labeled, tested E‑Stops.
- Operations SHALL follow institutional lab policies and supervision requirements.
Recommended
- Document hazard analyses and mitigations; update after each test.
- Practice lockout/tagout (LOTO) where applicable and train operators.
This safety case applies to both tracks; Mode Physical (P) carries additional risk due to physical equipment. See also Competition → Safety for general principles.